This report shows the number of days for each lead time segment as defined below.
For a better rendering, the report should be opened in Google Chrome browser.
The central date used to show the data is the order confirmation date in MSF Supply. This means that an order created in year n and confirmed in year n+1 will be shown in the year n+1 data here.
Overall filter : OCB delivered clients only.
Field | Remarks |
---|---|
Transport Mode | Transport mode of the freight. If null or no freight, it is the transport mode of the OP |
Dispatch Code | Delivery code defined in MSF Supply, usually associated with the capital |
Country | Mission |
Project Code | Identification code for project |
Orderline Count | Number of order lines (OP) |
Order Type | It shows the order type (MED or LOG) as in the OP |
IsEmergency | The order was handled as an emergency in MSF Supply, i.e. prioritized and managed with an emergency number |
Is TechOrder | Order lines handled as Technical orders |
IsArticleKC | Keep cool goods: KC1, KC1*, KC2, KC2*, KC2SA, KCC Keep Cool 2-8 °C |
IsDossierGreenLight | Allow to filter the lines which have been treated with or without a green light from the mission |
With GreenLight / Without GreenLight | Order lines for a country with or without pre-clearence requirement |
S02 Validation LT | Lead time (LT) between the order creation in the Portal and the final validation from mission and/or cell for transmission to MSF Supply. |
S03 Confirmation LT | Lead time between fthe final validation from mission and/or cell for transmission to MSF Supply and the confirmation of the OP in MSF Supply. |
S04 Preparation LT | Lead time between the confirmation of the OP in MSF Supply and when the orderline is ready to ship (RTS) which means prepared and invoiced. |
S04.1 Consolidation LT | Lead time between when the orderline is RTS and the freight creation. |
S05 Documentation LT | Lead time between the freight creation and the request for green light if context with go ahead |
S06 Pre-clearance LT | Lead time between the request for green light and when the mission gave the green light for launching the freight (for context with go ahead). |
S07 Freight preparation LT | Lead time between the freight creation (or the green light date for context with go ahead) and the moment the freight is shipped from MSF Supply. |
S08 Transportation LT | Lead time between the freight shipment in MSF Supply and the arrival date in the port of destination. |
S09 Reception LT | Lead time between the arrival date in the port of destination and the mission reception confirmation (if reception is confirmed by the mission) |