Field | Remarks |
---|---|
Transport Mode | Transport mode of the freight. If null or no freight, it is the transport mode of the OP |
Dispatch Code | Delivery code defined in MSF Supply, usually associated with the capital |
Country | Mission |
Project Code | Identification code for project |
Orderline Count | Number of order lines (OP) |
Order Type | It shows the order type (MED or LOG) as in the OP |
IsEmergency | The order was handled as an emergency in MSF Supply, i.e. prioritized and managed with an emergency number |
Is TechOrder | Order lines handled as Technical orders |
IsArticleKC | Keep cool goods: KC1, KC1*, KC2, KC2*, KC2SA, KCC Keep Cool 2-8 °C |
IsDossierGreenLight | Allow to filter the lines which have been treated with or without a green light from the mission |
With GreenLight / Without GreenLight | Order lines for a country with or without pre-clearence requirement |
S02 Validation LT | Lead time (LT) between the order creation in the Portal and the final validation from mission and/or cell for transmission to MSF Supply. |
S03 Confirmation LT | Lead time between the final validation from mission and/or cell for transmission to MSF Supply and the confirmation of the OP in MSF Supply. |
S04 Preparation LT | Lead time between the confirmation of the OP in MSF Supply and when the orderline is ready to ship (RTS) which means prepared and invoiced. |
S04.1 Consolidation LT | Lead time between when the orderline is RTS and the freight creation. |
S05 Documentation LT | Lead time between the freight creation and the request for green light if context with go ahead |
S06 Pre-clearance LT | Lead time between the request for green light and when the mission gave the green light for launching the freight (for context with go aheadgreen light). |
S07 Freight preparation LT | Lead time between the freight creation (or the green light date for context with go aheadgreen light) and the moment the freight is shipped from MSF Supply. |
S08 Transportation LT | Lead time between the freight shipment in MSF Supply and the arrival date in the port of destination. |
S09 Reception LT | Lead time between the arrival date in the port of destination and the mission reception confirmation (if reception is confirmed by the mission) |